Use this form to notify the regulator of proposed Class 1 or 2 demolition work.
Regulation 142F requires a person who wishes to do Class 1 demolition work or Class 2 demolition work in accordance with AS 2601 is to notify the regulator at least 5 working days before the work is intended to begin.
Regulation 142G requires a person who wishes to do Class 1 demolition work or Class 2 demolition work not in accordance with AS 2601 is to apply, at least 10 working days before the work is intended to begin, to the regulator for approval to do the work.
For demolition work involving the use of explosives, 15 working days’ notice is required. Demolition work involving explosives is not to begin unless approval has been provided by the regulator.